[mythtv-users] So: how *could* CBS solve the sports delay, problem

Michael T. Dean mtdean at thirdcontact.com
Tue Nov 1 16:17:26 UTC 2011


On 10/31/2011 01:51 PM, jedi wrote:
> On Mon, Oct 31, 2011 at 09:31:45AM -0400, Ken Mandelberg wrote:
>> I don't have a CBS solution. I do have a Myth suggestion that would help
>> a bit.
>>
>> What I do now is this. Sometime during 60 minutes I determine how late
>> it started. I override it with that many minutes. Then I override the
> ...something like an overtime-override button that could allow you to
> make the current recording run longer assuming it was still being recorded.

Ummm..  You just select the recording, then "Edit Schedule" and set up 
an override for it.  In MythWeb, you see, "Currently recording: Edit" 
and select that, then set up an override for it.  No need for a special 
button--just put a "this episode" override on the in-progress recording.

Mike


More information about the mythtv-users mailing list